Total Net Tonnage Required

<< Click to Display Table of Contents >>

Navigation:  Calculations > Equations > Heat Gain Equations >

Total Net Tonnage Required

Previous pageReturn to chapter overviewNext page

Net Tons = (Qs + QL) / 12,000

Where:

 

 Net Tons        = The required net tonnage of the HVAC unit, Tons
 Qs                        = Total sensible heat gain on building, Btuh
 QL                        = Total latent heat gain on building, Btuh
 12,000                        = A constant, 12,000 Btuh/ton

 

Ref:        ASHRAE 1985 Fund. - Page 37.2

 

Note:  See the Percent Sensible Capacity topic for information about meeting both the sensible and latent loads with Recommended tons rather than net tons.